The BQE Plan, Park by Park, From the Brooklyn Heights Promenade to Squibb Bridge

At the BQE town hall at Brooklyn Borough Hall on the last Thursday in October, the crowd was large enough that some people were turned away and put on a waitlist, according to the Brooklyn Eagle. After the formal presentation, attendees gathered at poster-board stations and around a large 3D model of the expressway built by Bjarke Ingels Group. DOT staff wrote down comments and then read back lists of the questions they had heard.

Most of the plan is a highway engineering document. If you live in Brooklyn Heights, though, the part of it you will feel is the list of parks. The Promenade gets the clearest promise in DOT's own materials. The plan's details are firmest, and least settled, at the north end of the neighborhood, where Columbia Heights meets Middagh Street. Harry Chapin Playground, Hillside Dog Park, Squibb Park and the bridge down to Pier 1 all sit there, next to the point where the second temporary highway would leave Columbia Heights.

The Promenade Has a Commitment in Writing

The project is called BQE Central. It covers the stretch from Sands Street to Atlantic Avenue, including the triple cantilever beneath the landmarked Promenade. DOT describes it as a rehabilitation of the existing structure in its current configuration, at a cost of up to $4 billion with no federal money. Gothamist reported that the work would replace deck joints, concrete and rebar and improve drainage, railings and lighting, with the rebuilt structure designed to last 40 years.

On the Promenade, DOT's October 6 presentation says the agency "will maintain access to portions of the Promenade at all times during construction, to the extent feasible." Transportation Commissioner Michael Flynn told Gothamist that sections of the Promenade would close, that at least one portion would always stay open, and that the temporary roadway would be "tucked out of view" from the walkway.

Neighbors who were here in 2018 will remember why that wording matters. The temporary-highway plan from that year, which the de Blasio administration later dropped, would have closed the Promenade for six years. Under DOT's schedule, construction is years away.

Columbia Heights and Middagh Street Is Where the Map Gets Crowded

Walk north on Columbia Heights from the end of the Promenade and you pass three small public spaces in about two blocks. NYC Parks lists Hillside Dog Park on Columbia Heights and Hicks Street, between Middagh and Vine Streets. Harry Chapin Playground is at Columbia Heights and Middagh Street and has a playground and spray showers. Its NYC Parks page notes that Chapin grew up in Brooklyn Heights and played there. Squibb Park is on Middagh between Columbia Heights and Furman Street. It is named for Dr. Edward Robinson Squibb, whose laboratories were nearby. From Squibb Park, the Squibb Park Bridge crosses down to the Greenway at Pier 1 in Brooklyn Bridge Park. That is the route many Heights households use to reach the waterfront without walking around by Old Fulton Street.

The second bypass would start here. The Draft Scope of Work, dated October 2, 2026, describes a temporary structure from Columbia Heights, possibly running above the Brooklyn Bridge, through Dumbo, and rejoining the highway west of the Manhattan Bridge.

DOT's slide names these three parks specifically. It says access to Squibb Park, Hillside Dog Park and Harry Chapin Playground "will be maintained to the extent feasible during construction," and that Harry Chapin Playground "will be reconstructed in conjunction with the Columbia Heights overpass rehabilitation." The Brooklyn Eagle's account of the town hall is more direct. It reports that the plan as it stands requires removing and fully rebuilding the north end of Columbia Heights and Harry Chapin Playground, along with partial or total closures of Squibb Playground, Hillside Park and the bridge entrance to Brooklyn Bridge Park. A source told the Eagle that because the playground sits on the overpass, it would be dismantled for at least 10 years under the bypass plan.

The overpass itself has a recent history. The Eagle reports that the Columbia Heights overpass was rebuilt this past August as part of DOT's interim BQE repairs. The new plan would take down that section and rebuild it higher. When the Eagle asked DOT staff at the town hall why, they said they did not have that information. In practice, a family that uses the spray showers at Harry Chapin in summer or crosses Squibb Bridge to Pier 1 on weekends lives near the part of the plan where DOT's wording is most qualified.

Below the Promenade, Furman Street Gets a Highway of Its Own

The first bypass would sit lower. The Draft Scope places it beside the triple cantilever, in the Furman Street right-of-way, from north of Atlantic Avenue to Columbia Heights. At the town hall, DOT Chief Strategy Officer Tiffany-Ann Taylor described it as a two-level structure at the level of the Queens-bound lanes. The Eagle reported that it would run 4 feet from the windows of some residences at 360 Furman Street. Building the temporary highways would take two years, and taking them down would take another two.

Brooklyn Bridge Park is on the far side of Furman Street, and the Draft Scope commits DOT to studying two effects there. First, the bypasses would add new structures above and next to sunlight-sensitive areas, including Brooklyn Bridge Park and city parkland. Because they may stand for several years, the environmental review will assess the shadows they cast. Second, the Eagle notes the park's landscaped berms, which were built to block highway sound and pollution. When a similar plan came up in 2023, the Brooklyn Bridge Park board and Conservancy wrote that it would destroy that effect.

The Draft Scope states the general point plainly. Rebuilding the roadway "may temporarily restrict access to parks," and the environmental study will look at ways to avoid, minimize or offset construction effects on parkland.

The South End and the Dumbo Side

The list continues past the Heights. The Draft Scope's open-space chapter names Adam Yauch Park, Anchorage Plaza, Clumber Corner and Bar and Grill Park among the parks next to the project area. The Eagle includes all four among the partial or total closures it reports.

Adam Yauch Park is at the southern edge, at Atlantic Avenue, Columbia Place and State Street. NYC Parks lists a full basketball court and a half court, a community garden and greenhouse, a fitness area, open play space and a dog run. It was called Palmetto Playground until May 3, 2013, when it was renamed for the Beastie Boys founder, who grew up playing there.

At the north end, on the Dumbo side, NYC Parks places Anchorage Plaza at Fulton, York, Washington and Prospect Streets by the Brooklyn Bridge. Clumber Corner runs along the BQE and Prospect Street between Washington and Adams Streets. If the second bypass is built as described, these two spaces sit along its path.

The Calendar Runs to 2040

None of this happens soon. DOT has begun the City Environmental Quality Review and will prepare an Environmental Impact Statement. The Draft Scope expects construction to start in 2029 and finish before 2040. Gothamist's August account gives slightly different milestones: temporary roadway construction starting in 2030, rehabilitation of the triple cantilever starting by 2032, and the restored highway open by 2040. Flynn told Gothamist that "the structure's safe right now," and that the city has run out of time for interim repairs alone.

The design can still change. At the town hall, Council Member Lincoln Restler said, "I don't think anybody likes what the administration has put forward." Assembly Member Jo Anne Simon said, "We need to be made happy." Flynn, who appeared near the end of the meeting, called the bypass "a starting point" and said DOT would consider other feasible approaches. Lara Birnback, executive director of the Brooklyn Heights Association, told the Eagle that "there are still many more questions than answers."

The project page lists a Draft Environmental Impact Statement and public meetings for late 2027. That document is where DOT will study construction effects on parks, including the Promenade, Squibb Park and Harry Chapin Playground.

If your home is near Columbia Heights, Furman Street or the Promenade, or you are looking at one, where a building sits relative to Squibb Park, Harry Chapin Playground and the planned Furman Street bypass is a fair thing to weigh alongside light, layout and price. Lena Simpson would be glad to talk through specific buildings in Brooklyn Heights and Dumbo with you. Request a Personalized Consultation.